20 Apr, 2026Executive summary
Advanced Barroso Lithium Project with a 40% increase in JORC Mineral Resource to 39.1Mt at 1.05% Li₂O and a 41% rise in Measured and Indicated Resources to nearly 27Mt.
Secured a non-reimbursable Portuguese State grant of up to €110 million and maintained strong cash reserves after raising £14.6 million in equity.
Progressed Definitive Feasibility Study (DFS) and environmental licensing, targeting DFS and RECAPE completion in July 2026 and first production in 2028.
Strengthened leadership team and expanded local presence, including a new office and increased stakeholder engagement.
Financial highlights
Loss from continuing operations decreased to £4.0m in 2025 from £4.4m in 2024, an 11% reduction.
Administrative expenses rose 4% to £4.4m; foreign exchange gain of £0.2m versus a £0.4m loss in 2024.
Year-end cash and cash equivalents stood at £17.2m, with an additional £5.0m in long-term deposits.
Intangible assets increased by 42% to £30.8m, reflecting ongoing project investment.
Total equity attributable to shareholders rose to £50.9m from £39.2m year-over-year.
Outlook and guidance
DFS and RECAPE submission expected in July 2026; construction targeted for 2027 and first production in 2028.
Focus on advancing project finance, commercial offtake agreements, and stakeholder integration.
Lithium market conditions have improved, with spodumene prices rising 90% in 2025 and further gains in 2026.
Latest events from Savannah Resources
- Resource growth, grant funding, and strong market support drive progress toward 2028 production.SAV
Status update20 Apr 2026 - AMG partnership and record cash position drive Barroso Lithium Project toward 2027 production.SAV
H1 20242 Apr 2026 - Resource upgraded 40%, DFS delayed to 2026, cash boosted by £4.78m fundraise.SAV
H1 20252 Apr 2026 - Barroso Lithium Project advanced with new partnership, strong cash, and EU 'Strategic Project' status.SAV
H2 20242 Apr 2026