Logotype for Savannah Resources plc

Savannah Resources (SAV) Status update summary

Event summary combining transcript, slides, and related documents.

Logotype for Savannah Resources plc

Status update summary

7 Oct, 2026

Project profile and economics

  • Phase I DFS: 20Mt JORC reserve, 14-year mine life, 1.5Mtpa throughput, 183ktpa average SC5.5 concentrate and 70% recovery target.

  • US$418m initial CAPEX, including pre-strip and contingency; US$323m net of the US$95m State Grant contribution. The grant awarded was €110m.

  • Post-tax NPV8 of US$913m, IRR of 43.2% and payback of 1.9 years; total EBITDA of US$3.2bn and free cash flow of US$1.9bn.

  • SC6-equivalent C1 cost of US$516/t and AISC of US$705/t, both in the second quartile of the 2030 global cost curve.

  • Open-pit DMS-flotation design includes dry-stack tailings, water collection and recycling, and a planned power connection with 80% renewable power.

Funding and commercial strategy

  • September US$40m raise lifted cash and short-term treasury reserves fourfold to ~US$53m; shares in issue rose 21%, and European investors contributed 99% of funds raised.

  • Largest shareholders participated; the institutional placing was oversubscribed and partly scaled back. Institutional ownership rose above 18%, including ~5 percentage points from battery-metals and mining-specialist funds.

  • Reserves support pre-construction work and project development while maintaining the timetable; total financing need is ~$450m, including working capital and financing costs.

  • Financing assumptions include 60–65% debt, a state grant, existing cash and further equity; conditional agreements targeted by year-end 2026 and financial close by Q1 2027.

  • Offtake strategy targets 70–75% of production under contract, with the balance retained for spot-market flexibility; a second agreement was targeted for Q4 2026.

Delivery milestones

  • Second easements fieldwork was nearing completion, with geotechnical and hydrogeological objectives met; RECAPE submission planned for Q4 2026 and in advanced preparation.

  • FEED and procurement work began for key equipment; management expected no negative CAPEX surprises, with major equipment down payments typically 10–20%.

  • Pre-construction drilling is underway; recruitment is targeting ~30 additional roles, with more than 3,000 applicants for current openings.

  • First concentrate targeted for late 2028 to early 2029; the schedule includes FID, access and power infrastructure, plant construction and commissioning.

  • Dual-listing preparation started; a European venue, potentially Euronext Lisbon, was considered likely in H1 2027 alongside AIM.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Savannah Resources