Savannah Resources (SAV) H1 2026 earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for Savannah Resources plc

H1 2026 earnings summary

18 Sep, 2026

Executive summary

  • Completed Phase 1 Definitive Feasibility Study (DFS) for a 14-year lithium project with robust economics and environmental standards.

  • Secured a non-reimbursable Portuguese State grant of up to €110m, reducing initial capex by 23%.

  • Achieved maiden JORC Probable Ore Reserve of 20.0Mt at 0.99% Li₂O and updated Mineral Resource of 39.2Mt at 1.05% Li₂O.

  • Signed ten MoUs with local and regional stakeholders, advancing land access and community engagement.

  • Progressed environmental licensing, land acquisition, and project finance discussions.

Financial highlights

  • Ended H1 2026 with GBP 17.1m in cash (GBP 12.2m available for development), up from GBP 11.9m YoY.

  • Losses from continued operations increased 34% YoY to GBP 2.0m due to higher admin expenses and lower FX gains.

  • Intangible assets grew 5% to GBP 32.3m; total assets at GBP 54.4m.

  • No revenue generated; operations remain pre-production.

Outlook and guidance

  • Targeting conditional project finance and a second offtake agreement by end-2026.

  • Final Investment Decision (FID) expected in early 2027; construction to start later in 2027, first concentrate by late 2028.

  • Key technical priorities: complete fieldwork, advance FEED, submit RECAPE, secure bypass road DIA.